Sunday, 16 February 2025

Project Performance Metrics Calculation

Project Performance Metrics Calculation

Project Performance Metrics Calculation

1. Given Data

  • Budget at Completion (BAC) = $4000
  • Total Project Duration = 4 years (48 months)
  • Elapsed Time = 17 months
  • Work Completed = 35% (0.35)
  • Actual Cost (AC) = $1500

2. Calculations

  • Planned Value (PV) = (Planned % Complete) * BAC
    • Planned % Complete = 17 / 48
    • PV = (17/48) * 4000 = $1416.67
  • Earned Value (EV) = (Actual % Complete) * BAC
    • EV = 0.35 * 4000 = $1400
  • Cost Variance (CV) = EV - AC
    • CV = 1400 - 1500 = -$100
  • Cost Performance Index (CPI) = EV / AC
    • CPI = 1400 / 1500 = 0.933
  • Schedule Variance (SV) = EV - PV
    • SV = 1400 - 1416.67 = -$16.67
  • Schedule Performance Index (SPI) = EV / PV
    • SPI = 1400 / 1416.67 = 0.988
  • Estimate at Completion (EAC) = BAC / CPI
    • EAC = 4000 / 0.933 = $4285.71
  • Estimate to Complete (ETC) = EAC - AC
    • ETC = 4285.71 - 1500 = $2785.71
  • Variance at Completion (VAC) = BAC - EAC
    • VAC = 4000 - 4285.71 = -$285.71
  • To-Complete Performance Index (TCPI) = (BAC - EV) / (BAC - AC)
    • TCPI = (4000 - 1400) / (4000 - 1500) = 0.933

3. Results Table

Metric Value
BAC $4000
PV $1416.67
EV $1400
AC $1500
CV -$100
CPI 0.933
SV -$16.67
SPI 0.988
EAC $4285.71
ETC $2785.71
VAC -$285.71
TCPI 0.933

4. Summary

The project performance metrics indicate that the project is slightly behind schedule (SPI < 1) and over budget (CPI < 1). The estimated cost at completion (EAC) is projected to be higher than the initial budget (BAC), leading to a negative variance at completion (VAC). If cost efficiency is not improved, the project will exceed its allocated budget.

No comments:

Post a Comment