Key Points:
-
Backward Pass Overview:
- The backward pass calculates the Late Finish (LF) and Late Start (LS) for each activity in a project network diagram.
- LF: The latest an activity can finish without delaying the project.
- LS: The latest an activity can start without delaying the project.
-
Backward Pass Steps:
- Start at the end of the diagram (last activity).
- Begin with the critical path duration (e.g., 11 in this example).
- Use the formula:
LS = LF - Duration + 1.
-
Example Backward Pass Calculation:
- Activity E:
- LF = 11 (critical path duration), Duration = 2.
- LS = 11 - 2 + 1 = 10.
- Activity C:
- LF = 10, Duration = 4.
- LS = 10 - 4 + 1 = 7.
- Activity D:
- LF = 9 (smallest LF of converging paths to Activity B), Duration = 3.
- LS = 9 - 3 + 1 = 7.
- Activity B:
- LF = 7 (smallest LF of converging paths), Duration = 2.
- LS = 7 - 2 + 1 = 6.
- Activity A:
- LF = 4, Duration = 3.
- LS = 4 - 3 + 1 = 2.
- Activity E:
-
Converging Paths in the Backward Pass:
- At path convergence points, select the smallest LF among the converging paths for the backward calculation.
- This ensures that the subsequent activities start as late as possible without delaying the project.
-
Critical Path and Slack:
- Activities on the critical path have no slack (Slack = 0).
- LF = EF and LS = ES for critical path activities.
- Non-critical path activities (e.g., Activity D) have slack, calculated as:
- Slack = LF - EF or Slack = LS - ES.
- Activities on the critical path have no slack (Slack = 0).
-
Practical Example of Slack:
- Activity D:
- LF = 9, EF = 8, LS = 7, ES = 6.
- Slack = 9 - 8 = 1 (or 7 - 6 = 1).
- Activity D:
-
Backward Pass Tips:
- When going backward:
- Use the largest number at convergence points for the forward pass.
- Use the smallest number at divergence points for the backward pass.
- Focus on calculating one step at a time, ignoring unrelated numbers until needed.
- When going backward:
-
Outcome of the Backward Pass:
- The diagram now contains all four values for each activity: ES, EF, LS, LF.
- Identifies:
- Total project duration.
- Critical path activities (no slack).
- Non-critical activities with slack.
-
Encouragement and Next Steps:
- If the backward pass is unclear, re-watch the video and practice with simpler and more complex examples.
- The backward pass is as manageable as the forward pass when broken into logical steps.
Summary:
The backward pass determines the Late Finish (LF) and Late Start (LS) for activities in a project network diagram by calculating backward from the project’s end. The process identifies critical path activities with no slack and non-critical activities with slack, which can be delayed without affecting the project. The backward pass uses the formula LS = LF - Duration + 1 and requires selecting the smallest LF at convergence points. By completing the forward and backward passes, the network diagram provides a complete schedule, highlighting the critical path and slack for effective project management.
No comments:
Post a Comment