Sequence Activities

 

Summary of the "Sequence Activities" Process

  1. Definition:

    • The Sequence Activities process involves arranging activities in the order they need to be performed, based on dependencies and relationships.
    • This ensures a logical and efficient workflow, forming the basis for developing a project schedule.
  2. Purpose:

    • To define the logical sequence of activities for maximum efficiency and effective resource use.
    • To create the Project Schedule Network Diagram, a graphical representation of activity sequences.
  3. Key Characteristics:

    • Activity Relationships:
      • Identifies how activities are linked (e.g., Finish-to-Start, Start-to-Start).
    • Dependencies:
      • Defines mandatory, discretionary, internal, and external dependencies.
    • Leads and Lags:
      • Adds overlaps or delays between activities as needed.
  4. Key Inputs:

    • Activity List and Attributes:
      • A detailed list of activities and their characteristics.
    • Milestone List:
      • Significant project milestones to consider in sequencing.
    • Project Management Plan:
      • Includes the Schedule Management Plan for guidance.
  5. Key Tools and Techniques:

    • Precedence Diagramming Method (PDM):
      • A method used to create the Project Schedule Network Diagram by defining relationships between activities:
        • Finish-to-Start (FS): Activity A must finish before Activity B starts (most common).
        • Start-to-Start (SS): Activities start simultaneously but may finish at different times.
        • Finish-to-Finish (FF): Activities finish at the same time but may start at different times.
        • Start-to-Finish (SF): Rarely used; an activity must start before another can finish.
    • Dependency Determination:
      • Mandatory Dependencies (Hard Logic):
        • Example: Pouring concrete before building walls.
      • Discretionary Dependencies (Soft Logic):
        • Example: Painting walls before installing carpet (optional order).
      • External Dependencies:
        • Example: Waiting for regulatory approval or a shipment.
      • Internal Dependencies:
        • Example: Dependencies controlled within the team.
    • Leads and Lags:
      • Lead: Overlapping activities to shorten the schedule (e.g., start taping walls while removing furniture).
      • Lag: Delaying the start of a successor activity (e.g., wait a day for paint to dry before moving furniture back).
  6. Key Outputs:

    • Project Schedule Network Diagram:
      • A graphical representation of activity sequencing, showing the logical flow of work.
      • Example: Start → Activity A → Activity B → Activity C → Finish.
    • Project Document Updates:
      • Updates to activity attributes, assumptions, and constraints.
  7. Applications in Practice:

    • Construction:
      • Foundation must be built before framing; framing must be completed before roofing.
    • Software Development:
      • Backend setup must be completed before frontend development begins.
    • Event Planning:
      • Venue booking must precede vendor confirmations and event setup.
  8. Highlighted Points:

    • Logical Flow:
      • Proper sequencing ensures tasks are completed efficiently and on time.
    • Dynamic Nature:
      • The sequence may change as dependencies or constraints evolve during the project.
    • Real-Life Usage:
      • Tools like Microsoft Project automate the creation of Network Diagrams using PDM.
  9. Importance:

    • Provides the foundation for estimating activity durations and creating the project schedule.
    • Helps identify critical dependencies and potential bottlenecks.
  10. Key Takeaway:

    • The Sequence Activities process organizes tasks into a logical order, creating a clear workflow and enabling effective schedule development. A well-sequenced project minimizes delays and maximizes efficiency. "Sequence logically, schedule effectively, deliver confidently."