Summary of the "Sequence Activities" Process
-
Definition:
- The Sequence Activities process involves arranging activities in the order they need to be performed, based on dependencies and relationships.
- This ensures a logical and efficient workflow, forming the basis for developing a project schedule.
-
Purpose:
- To define the logical sequence of activities for maximum efficiency and effective resource use.
- To create the Project Schedule Network Diagram, a graphical representation of activity sequences.
-
Key Characteristics:
- Activity Relationships:
- Identifies how activities are linked (e.g., Finish-to-Start, Start-to-Start).
- Dependencies:
- Defines mandatory, discretionary, internal, and external dependencies.
- Leads and Lags:
- Adds overlaps or delays between activities as needed.
- Activity Relationships:
-
Key Inputs:
- Activity List and Attributes:
- A detailed list of activities and their characteristics.
- Milestone List:
- Significant project milestones to consider in sequencing.
- Project Management Plan:
- Includes the Schedule Management Plan for guidance.
- Activity List and Attributes:
-
Key Tools and Techniques:
- Precedence Diagramming Method (PDM):
- A method used to create the Project Schedule Network Diagram by defining relationships between activities:
- Finish-to-Start (FS): Activity A must finish before Activity B starts (most common).
- Start-to-Start (SS): Activities start simultaneously but may finish at different times.
- Finish-to-Finish (FF): Activities finish at the same time but may start at different times.
- Start-to-Finish (SF): Rarely used; an activity must start before another can finish.
- A method used to create the Project Schedule Network Diagram by defining relationships between activities:
- Dependency Determination:
- Mandatory Dependencies (Hard Logic):
- Example: Pouring concrete before building walls.
- Discretionary Dependencies (Soft Logic):
- Example: Painting walls before installing carpet (optional order).
- External Dependencies:
- Example: Waiting for regulatory approval or a shipment.
- Internal Dependencies:
- Example: Dependencies controlled within the team.
- Mandatory Dependencies (Hard Logic):
- Leads and Lags:
- Lead: Overlapping activities to shorten the schedule (e.g., start taping walls while removing furniture).
- Lag: Delaying the start of a successor activity (e.g., wait a day for paint to dry before moving furniture back).
- Precedence Diagramming Method (PDM):
-
Key Outputs:
- Project Schedule Network Diagram:
- A graphical representation of activity sequencing, showing the logical flow of work.
- Example: Start → Activity A → Activity B → Activity C → Finish.
- Project Document Updates:
- Updates to activity attributes, assumptions, and constraints.
- Project Schedule Network Diagram:
-
Applications in Practice:
- Construction:
- Foundation must be built before framing; framing must be completed before roofing.
- Software Development:
- Backend setup must be completed before frontend development begins.
- Event Planning:
- Venue booking must precede vendor confirmations and event setup.
- Construction:
-
Highlighted Points:
- Logical Flow:
- Proper sequencing ensures tasks are completed efficiently and on time.
- Dynamic Nature:
- The sequence may change as dependencies or constraints evolve during the project.
- Real-Life Usage:
- Tools like Microsoft Project automate the creation of Network Diagrams using PDM.
- Logical Flow:
-
Importance:
- Provides the foundation for estimating activity durations and creating the project schedule.
- Helps identify critical dependencies and potential bottlenecks.
-
Key Takeaway:
- The Sequence Activities process organizes tasks into a logical order, creating a clear workflow and enabling effective schedule development. A well-sequenced project minimizes delays and maximizes efficiency. "Sequence logically, schedule effectively, deliver confidently."