Summary of the PERT Formula (Program Evaluation and Review Technique)
-
Definition:
- The PERT formula is a statistical tool used in project management to estimate the duration or cost of an activity based on three values:
- Optimistic (O): Best-case scenario.
- Realistic (R): Most likely scenario.
- Pessimistic (P): Worst-case scenario.
- The PERT formula is a statistical tool used in project management to estimate the duration or cost of an activity based on three values:
-
Purpose:
- To calculate a weighted average duration or cost for an activity.
- To account for uncertainties and variability in estimates, providing a realistic forecast.
-
PERT Formula:
- Expected Duration (E):
- This formula gives more weight to the realistic estimate (4R).
- Expected Duration (E):
-
Standard Deviation:
- Measures the range of uncertainty in the estimate:
- Indicates the expected variation from the mean estimate.
- Measures the range of uncertainty in the estimate:
-
Triangular Distribution:
- A simpler average of the three values:
- Does not weight the realistic estimate and is less commonly used.
- A simpler average of the three values:
-
Example:
- Scenario: Estimate the time to paint a room.
- Optimistic (O): 2 days.
- Realistic (R): 4 days.
- Pessimistic (P): 12 days.
- Calculate Expected Duration (PERT):
- Calculate Standard Deviation (SD):
- Range of Estimate:
- : The activity will take between 3.3 and 6.7 days.
- Scenario: Estimate the time to paint a room.
-
Second Example:
- Scenario: Estimate time for another task.
- Optimistic: 10 days.
- Realistic: 15 days.
- Pessimistic: 40 days.
- Calculate Expected Duration:
- Standard Deviation:
- Scenario: Estimate time for another task.
-
Applications:
- Exams (PMP, CAPM):
- PERT is a commonly tested concept; know the formulas and practice calculations.
- Real Life:
- Used in government projects and large-scale organizations to estimate timelines and budgets.
- Tools like Microsoft Project support PERT calculations.
- Exams (PMP, CAPM):
-
Advantages:
- Provides a more realistic estimate by weighting the most likely outcome.
- Incorporates uncertainty and helps account for risks in activity durations.
-
Highlighted Points:
- Memorize the PERT formula:
- Understand the difference between PERT (weighted average) and Triangular Distribution (simple average).
- Use the Standard Deviation formula to calculate the range of estimates.
Key Takeaway:
The PERT formula is a valuable tool for estimating durations or costs with realistic and data-driven precision. It considers uncertainty, improves planning accuracy, and is widely used in exams and real-life projects. "Estimate thoroughly, account for risks, deliver confidently."
No comments:
Post a Comment