Summary of the "Estimate Activity Durations" Process
-
Definition:
- The Estimate Activity Durations process determines the number of work periods required to complete each activity in the project schedule.
- A work period can be measured in minutes, hours, days, weeks, or months, depending on the project.
-
Purpose:
- To estimate how long each activity will take based on available resources, project constraints, and dependencies.
- Provides input for creating the project schedule.
-
Key Characteristics:
- Expert-Based:
- Estimates should be made by those most familiar with the work (e.g., subject matter experts, team members).
- Dynamic:
- Considers factors like resource availability, skill levels, and risks.
- Expert-Based:
-
Key Inputs:
- Activity List and Attributes:
- Provides the activities requiring duration estimates.
- Resource Requirements:
- Indicates resources available for each activity and their impact on duration.
- Resource Calendar:
- Identifies when resources are available for work.
- Project Management Plan:
- Guides estimation through the Schedule Management Plan.
- Activity List and Attributes:
-
Key Tools and Techniques:
- Estimation Methods:
- Analogous Estimation (Top-Down):
- Uses historical data for similar activities.
- Quick and cost-effective but less accurate.
- Example: "It took 2 days to paint a similar room, so this room will also take 2 days."
- Bottom-Up Estimation:
- Breaks work into smaller pieces and estimates each in detail, then aggregates the results.
- Time-consuming but highly accurate.
- Example: Measure and calculate painting time for every wall individually.
- Parametric Estimation:
- Uses statistical models or formulas.
- Example: "Each square foot takes 10 minutes to paint; with 200 square feet, it will take ~33 hours."
- Three-Point Estimation:
- Uses optimistic, realistic, and pessimistic estimates to calculate a weighted average.
- Formula: (covered in detail in PERT calculations).
- Reserve Analysis:
- Adds buffers to account for risks or uncertainties (e.g., extra days for unexpected delays).
- Analogous Estimation (Top-Down):
- Decision Making:
- Teams collaborate to finalize realistic durations.
- Estimation Methods:
-
Key Outputs:
- Duration Estimates:
- The estimated time required for each activity.
- Includes ranges (e.g., 10 days ± 2 days) to account for variability.
- Basis of Estimates:
- Documentation of how estimates were developed, including assumptions, constraints, and methodologies.
- Duration Estimates:
-
Examples:
- Construction:
- Painting a room is estimated to take 3 days based on past projects and resource availability.
- Software Development:
- Writing a login feature is estimated at 5 days ± 1 day based on developer experience.
- Event Planning:
- Booking a venue is estimated at 2 weeks due to regulatory approval requirements.
- Construction:
-
Key Concepts:
- Influence of Resources:
- Increasing resources (e.g., more workers) may reduce duration but might also increase costs or coordination challenges.
- Accuracy Levels:
- Analogous estimates are faster but less accurate, while bottom-up estimates are detailed but time-intensive.
- Range of Estimates:
- Adding ranges to estimates provides flexibility and transparency.
- Influence of Resources:
-
Importance:
- Accurate duration estimates are critical for developing a reliable project schedule.
- Helps manage stakeholder expectations by providing realistic timelines.
-
Highlighted Points:
- Dynamic Adjustments:
- Estimates may evolve as new information becomes available (progressive elaboration).
- Collaboration:
- Engage team members and experts for accurate estimates.
- Buffering:
- Use reserve analysis to account for uncertainties.
- Dynamic Adjustments:
Key Takeaway:
The Estimate Activity Durations process ensures realistic timeframes for each activity, forming the foundation for a reliable project schedule. By leveraging various estimation techniques and expert input, project managers can anticipate challenges and create achievable timelines. "Estimate wisely, schedule effectively, deliver confidently."