Total Float vs. Free Float

 

Key Points:

  1. Understanding Total Float vs. Free Float:

    • Total Float:
      • The amount of time an activity can be delayed without delaying the entire project.
      • Activities on the critical path have no total float.
    • Free Float:
      • The amount of time an activity can be delayed without delaying the next activity.
      • Critical path activities also have no free float, as delays propagate to subsequent activities.
  2. Free Float Formula:

    • Free Float = Early Start (ES) of the Next Activity - Early Finish (EF) of the Current Activity - 1.
    • This formula highlights the time buffer between two sequential activities.
  3. Examples of Free Float Calculation:

    • Activity A:
      • EF = 3, ES of next activity (B) = 4.
      • Free Float = 4 - 3 - 1 = 0.
      • A has no free float.
    • Activity B:
      • EF = 5, ES of next activities (C or D) = 6.
      • Free Float = 6 - 5 - 1 = 0.
      • B has no free float due to its critical path role.
    • Activity D:
      • EF = 8, ES of next activity (E) = 10.
      • Free Float = 10 - 8 - 1 = 1.
      • D has a free float of 1, meaning it can be delayed by one day without affecting E.
  4. Critical Path and Free Float:

    • Activities on the critical path typically have no free float or total float because any delay impacts the next activity and the entire project.
    • Non-critical path activities, such as D in this example, can have free float if their delay doesn’t immediately affect subsequent tasks.
  5. Key Differences:

    • Total Float:
      • Measures flexibility regarding the entire project timeline.
    • Free Float:
      • Measures flexibility regarding the next activity in the sequence.
  6. Practical Importance:

    • Knowing both total and free float helps in:
      • Resource allocation: Prioritizing critical tasks.
      • Risk management: Identifying where delays may occur without broader impact.
    • Free float provides a more granular view of individual task dependencies.
  7. Encouragement for Learners:

    • The calculations for free float are straightforward when the formulas are understood and applied step by step.
    • Practice with similar diagrams ensures clarity and confidence for exams and real-world applications.

Summary:

Free float differs from total float in that it measures how much an activity can be delayed without delaying the next activity, rather than the entire project. Using the formula Free Float = ES (Next Activity) - EF (Current Activity) - 1, it is easy to calculate free float for any task. Critical path activities typically have no free float or total float, while non-critical activities may have both. Understanding and differentiating these concepts is crucial for project management, enabling better planning, resource allocation, and risk mitigation. The next step involves practicing these calculations with additional diagrams for mastery.